BOULEVARD
Land fronting Bristol Street and Belgrave Middleway
Birmingham, B5 7AY
View the site map HERE.
PROJECT TEAM:
Developer: Investin PLC (*Relton Property Investments Ltd*)
Architects: Wake Morley Architects
Development Manager: The Construction Consultants
Quantity Surveyor: TBC
Civil & Structural Engineer: TBC
M&E: Elite Building Services
Substructure, Mortar, Labour: Redstone Brickwork
Contractor: Bespoke Construction
Agent: Property & Design Associates
Value: £49 million
Planning Application Number: 2022/00913/PA
Development Loan: Octopus Real Estate (£53.5M)
Targeted Completion: TBC
BOULEVARD
Boulevard is under construction with the delivery of 278 one- and two-bedroom rental units in buildings ranging from four to 15-storeys.
Phase I will deliver an initial 145 one- & two-beds in phase one, across three buildings of four, six, and 15-storeys; Phase II will deliver the three remaining builds of five and six-storeys.
Residents living here will have access to a gym and cinema, spacious lounges, workspaces, a roof terrace and a podium courtyard, all of which fit the standard for the city’s burgeoning rental sector.
Bristol Street, images from Investin PLC - all are subject to change.
CONSTRUCTION PROGRESS:
May 2023 -
Piling has commenced at Boulevard, signalling a start of construction.
September -
February 2024 -
Drone photography by Stephen Giles.